Coil Transport System

Customer: ISD Dunaferr Zrt.

Buma Engineering was commissioned to design a Coil Transport System for ISD Dunaferr Zrt. The first construction section included the erection of a Coil Transport System to a simultaneously built Strip Pickling line. As a second section, the existing Coil Transfer System – starting at the Coiler – was rebuilt with new equipment.

The complete mechanical engineering of the whole Coil Transport System was realized within only 3 month.

Technical Data:
Cycle time: 117 seconds
Max. waist dimension: Ø2.250 x 1.560 mm
Min. waist dimension: Ø1.200 x 800 mm
Max. Bundle weight: 35 t