Gas Scrubber

Start of the project: March 2017

The planning phase took place until the shut down in close cooperation with the project team on site.

Start of erection: June until September 2018

Fa. Buma supported the assembly companies on site during the installation.

 

Scope of supply:

Basic engineering

gas scrubber in DUPLEX

foundation

Pipe layout incl. positioning of the valves and scrubber nozzles

complete steel structures incl. stairs and all maintenance equipment

Disassembly device of the existing vessel

 

Detail Engineering

• Foundation plans

• complete steel structures incl. stairs and all maintenance equipment

Technical Data:
Weight: 180 tons
Weight steel structures (platforms): 210 tons
Height of the scrubber: 33 m
Diameter of the scrubber: 6,5 m